What does CPM stand for in project scheduling?

Critical Path Management

Cost Performance Method

Critical Path Method (CPM)

CPM stands for Critical Path Method, a project scheduling technique that focuses on the sequence of tasks that determine the project’s finish date. By building a network of activities with their durations and dependencies, you can calculate the earliest start and finish for each task (forward pass) and the latest start and finish that won’t delay the project (backward pass). The tasks with zero slack—the critical path—set the minimum project duration because any delay in those tasks pushes the finish date. This makes CPM a powerful tool for prioritizing work, planning resources, and assessing schedule risk. The other terms aren’t standard scheduling concepts: one mixes with cost-performance metrics from earned value management, while the others aren’t recognized methods in scheduling.

Controlled Process Mapping

Next Question
Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy